Shawano County
Highway: WIS 22
Location: Between County B and Zingler Street & Main Street and County BE
Schedule: Project will start again in Spring 2020 to complete project. This is the last update for 2019.
Traffic impacts: All lanes are currently open to traffic. Single-lane closures will occur in Spring 2020 to complete remaining work between County BE and Airport Road.
Anticipated work scheduled for next week: Crews will remove temporary traffic control devices for winter.
Website: https://projects.511wi.gov/wis22resurf/
Waupaca and Wood Counties
Highway: WIS 110
Location: Between Wolf River Drive and WIS 96 in Fremont
Schedule: July 8, 2019 to November 22, 2019. Some work will be completed in Spring 2020. This is the last update for 2019.
Traffic impacts: WIS 110, Wolf River Bridge: Motorists can expect to encounter one lane crossing the bridge with temporary signals thru November 22.
Anticipated work schedule for next week: Contractor will finish installing guardrail, concrete work and install pavement markings to open the bridge. Some work will be completed in Spring 2020.