Length of project: On bridge
Cost: $916,000
Construction schedule: August 19, 2019 to November 2019
Description of work: This project will replace the existing structure on WIS 32 over the Pensaukee River with a new bridge and retaining wall. The project will also replace a wing wall on a box culvert and conduct concrete surface repair on another box culvert. Other construction elements under this contract includes excavating, grading, asphalt paving, beam guard, and signage.
October 7 to October 11: The contractor finished installing the steel sheeting for the retaining wall and finished pouring the concrete coping for the retaining wall. The contractor also placed heavy riprap and light rip rap. The contractor also placed pigmented surface sealer on the parapets and protective surface treatment on the bridge deck.
October 14 to October 18: The contractor will start pulverizing the existing asphalt, start excavating down to subgrade, and place base aggregate for the roadway approaches. The contractor will also start working on the box culvert wing replacement and the box culvert concrete surface repair.
Traffic impacts: WIS 32 will be closed at the bridge, and traffic will be detoured. Access to properties will be maintained. Southbound WIS 32 shoulder closures just north of Gohr Road and just south of Van Dornick Road.
Detour: The detour route for northbound WIS 32 will start at WIS 32 to WIS 29 to WIS 117 to WIS 22 to WIS 32. The detour for southbound WIS 32 will start at WIS 32 to WIS 22 to WIS 117 to WIS 29 to WIS 32.